Railroad Relies On Hulcher For #15 Switch Change At Rail Yard
Scope:
A #15 switch at the rail yard had been damaged. Since this switch was located at a rail yard it was close to several other tracks that were busy with traffi c. The railroad needed an experienced crew to get the switch changed out quickly and safely. Fortunately, they had a maintenance-ofway contract with Hulcher Services and brought in a Hulcher crew to get the work done.
Solution:
Hulcher Services took care of the switch change with an array of three track excavators and a wheel loader. Two excavators pulled the old switch from its spot and moved it safely to the side for disposal. The wheel loader came in to smooth the site and clear out the old ballast so the new switch would lay evenly on the surface. The three excavators and wheel loader then worked in concert to lift and place the new switch precisely in line with the rest of the track. The wheel loader finished Hulcher’s work, bucking the ballast for the railroad to tamp into place. The entire project was performed in close coordination with the railroad to minimize interfering with its ongoing operations at the yard.
Outcome:
In six hours the damaged switch had been removed and replaced with the professionalism and seamless proficiency Hulcher has developed through many years of experience. The railroad has a long relationship with Hulcher and relies on the skill of its operators to perform a wide range of maintenance-of-way projects like this one.
Hulcher Performs Switch Change on #20 Switch on Double Main
The railroad needed to change a #20 switch as part of their routine track maintenance program. The switch was on a double main, so the project had to be completed within very tight track windows.
Hulcher Clears Fire Damage For Bridge Repair, Performs Driftwood Removal From Bridge Piers
A fire on driftwood resulted in a bridge repair project for the railroad. During this work it became apparent that the driftwood was causing more concerns than just a fire threat.
New Railroad Crossing Improves Comfort and Safety for Local Commuters
A chronic problem for one Midwestern community was the old and worn-out railroad crossing in the center of town. The ride over the tracks was always a bumpy one and extremely hard on the vehicles that crossed it on a daily basis.